Contract: Al Araby Residential Complex

  •  TP01 Earthworks
    *Contract date: 10/04/2018
  •  TP02 Construction works for 8 buildings and 7 Villas.
    *Contract date: 30/09/2018
  • Interior work for Villa No.4 at ElARABY Residential Complex.
  • Interior work for Villa No.8 at ElARABY Residential Complex.

CONSTRUCTION OF:

  • 4 BUILDINGS TYPE A
  • 2 BUILDINGS TYPE A’
  • 1 BUILDING TYPE D
  • 1 BUILDING TYPE E
  • 5 VILLAS TYPE U
  • 1 VILA TYPE L
  • 1 VILA TYPE LM

IN TOTAL OF 8 BUILDINGS AND 7 VILLAS INCLUDING 6 PODUIMS

WORK SCOPE:

  1. EXCAVTION
  2. NECESSARY REPALCEMENT
  3. FOUNDATION (ISOLATED AND RAFT)
  4. INSULATION
  5. SKELETON WORK
  6. EXTERIOR BRICKWORKS
  7. FASCADE FINISHING
  8. BASEMENT FININSHING